Traffic diversions


Proposed Traffic Management Measures for the M3 Clonee to North of Kells Motorway Project:

                                                                       

Name of Road

Type of Traffic Management

Description of Traffic Management

Time Period

Existing N3 between Clonee and Blackbull

Temporary Speed Limit Restriction

Speed Limit Restriction

12 Months

M3 Southern Tie-in

Hardshoulder closures and traffic shunted over to different lanes to allow to construction to continue

Temporary diversions carrying two way traffic

6 months

Dunboyne Bypass

Road opening in two phases

Road Opening

August/September

Raynestown Lane

Road Closure

The diversion route is via Derrockstown Road

22/06/09 to 06/07/09

Dunshaughlin Link Road

Road Opening

Road Opening

July 09

Killmessan Road, Dowdstown

Road Closure

The diversion route is via Kilmessan and the existing N3

06/07/09 to 20/07/09

Dowdstown Road

Traffic lights

Single lane traffic

Works programmed to be completed by September

Ballybatter Road

Road Reopening

Road Opening

August 28th

Kilcarn Roundabout on the existing N3

Temporary diversions with two way traffic at all times

Minor diversions

Commencing August 09

All roundabouts in the vicinity of Kells

All traffic management restrictions to be removed

Road Opening

July 2009